Back to Project Portfolio

Port of Albany Offshore Wind at Beacon Island

Glenmont, NY
8 Months

Clearing & grubbing of 80 acres, site cut and fill, import and place fill, import and place surcharge stone, rock excavation, contaminated soil segregation and offsite disposal and site enabling.

Site Highlights

32M project, 1,000,000 TON of gravel and stone imported within 6 months, moved 120,000 CY onsite while importing gravel and stone, 15,000 TON of contaminated soil disposed offsite, 24,000 TON barged

Contact Us

Give a call at (518) 732-7782 or get in touch with us about how we can deliverer high quality, cost effective projects, that are on time and on budget.